Construction of a Classroom Block at Siamoono

This project will construct a 1 x 3 Classroom Block incorporating a staffroom at Siamoono School in Zambia. The education of 300 enrolled students, who often learn with several year groups in a classroom, will be transformed.

Construction will take roughly 3 months from delivery of materials. Start Date will be dependant on securing funding, and the rains.

Charity information: African Revival

African Revival logo
  • Need

    Need

    Siamoono Primary School currently has 3 classroom blocks – one of these being a temporary structure. For almost 300 pupils enrolled at the school this means that classes are often conducted for multiple grades in the same classroom. This makes effective lesson delivery incredibly difficult for the teachers, and makes it very hard for pupils to focus on their work.

    Solution

    The construction of this classroom block will complement an additional project we will be implementing at the school - latrine construction. The school serves 350 households and 750 children live in the community. Out of 500 children of school going age in the community, only 284 are enrolled at the school. Improved facilities will positively impact enrolment rates as community members be assured their children will be getting a quality education at the school.

  • Aims

    Aim 1

    Improve Academic Attainment at the School

    Activities

    » Providing a staffroom in the classroom block will give teachers at the school a place to plan their lessons.
    » Adequate numbers of classrooms will ensure that different year groups are not taught in the same room. This will help children to focus properly.

    By recording increases in the number of children passing their primary learning exams.


  • Impact

    Impact

    Encourage the local community to send their children to school, and understand how vital education is. Through monitoring of enrolment figures over a multi- year period.

    Risk

    1. Ensuring building works are not impacted by the rains -
    We have worked in the region since 2005 and are well equipped to manage this.
    2. Delay in Material Delivery -
    We have a memorandum of understanding with our suppliers that all materials must be delivered within 14 days.

    Reporting

    With a two page final donor report, sent via email or post. We also try to communicate about all projects on our social media channels.

  • Budget

    Budget - Project Cost: £20,604

    Loading graph....
      Amount Heading Description
      £20,604 Construction of CRB Total Project Costs
  • Background

    Location

    Siamoono is a rural Community School in Zambia, so does not receive government support. The school needs teachers housing before the government will post teachers there.

    Beneficiaries

    300 Currently enrolled pupils, and thousands more in years to come.

  • Why Us?

    Why Us?

    We are the only NGO working around Kaloma. We have years of experience in implementing this kind of construction project.

    Read more about the Charity running this project.

    People

    David Sangweni

    Construction Superviser. David has delivered more than 70 projects with AR Zambia since 2005.